Accra, Dec 9, GNA— The Government is to pay an additional GHC80 million for the completion of the Flowerpot flyover project supposed to be completed in 2018 at GHC67 million.
After a new variation order, the project, which commenced in 2016 and currently at 16 percent complete, is estimated to cost the country about GHC147 million.
The Public Interest Accountability Committee (PIAC) received this information when some members visited the project site near Spintex in Accra, for firsthand information on how GHC3.6 million of oil revenue was used in 2019 to finance the project.
A government official, explained to the team that the project stalled after four months of commencement due to the failure of the Government to honour a certificate that was raised by the contractor.
“…And so, he was awaiting invoices that were raised,” the official told PIAC members.
The official also told PIAC that a new project period had been set from January 2021 to January 2023 as the contractor had agreed to continue with the project after renegotiations.
The Vice-Chairman of PIAC, Mr Nasir Alfa Mohammed, advised that oil revenue should be invested in legacy projects that would have a significant impact on citizens.
“The situation where funds are invested in projects scattered around the country does not make the desired impact on citizens hence making it difficult to assess the impact and track how oil revenue Is being spent.”
Speaking about the flyover project, he said: “we cannot point to a significant impact of the oil money on that project and when we are mentioning projects that oil money has gone into, it is too insignificant for us to say oil money has gone into this”.
The team also inspected the 1.5-kilometer upgrade of the Powerland-Sakora Road in Madina, which was valued at GHC1.49 million with 90 per cent of funding coming from oil revenue.
Source: Ghana News Agency
More Stories
Government working on employment modules to re-engage toll workers – Deputy minister
Accra, The government is currently engaging with Toll and Route Management Limited to develop other employment modules for the re-engagement...
Youth against drugs project launched in Tamale
Tamale, May 19, GNA – Youth Against Drugs (YAD), a youth focused project, has been launched in Tamale by the Active Youth Global (AYG) in collaboration with Total Life Enhancement Centre, Ghana (TOLEC Ghana).The project seeks to raise awareness on the …
Ghana participates in fifth Global Conference on Elimination of Child Labour
Accra, May 19, GNA – Ghana is participating in the ongoing fifth African Global Conference on the Elimination of Child Labour on the theme, “We Can # End Child Labour”, which is underway in Durban, South Africa.Mr Bright Wireko Brobby, Deputy Minister …
Police move to tackle traffic congestion on Atonsu Agogo-Lake Bosomtwe Road
Kumasi, May 19, GNA – The Ashanti Regional Police Command has outlined measures to tackle traffic congestion on the Kumasi High School Junction-Atonsu Agogo-Dompoase stretch of the Atonsu Agogo-Lake Bosomtwe Road.A statement signed by Assistant Superin…
Prof. Kalamonia exceeded expectations in the 2020 elections, deserves to be retained – Savannah NPP Youth
A coalition of NPP Youth in the Savannah Region have argued that incumbent regional chairman, Alhaji Iddrisu Sulemana popularly called Professor Kalamonia deserves to be retained to consolidate the gains made in the region by the governing party.They m…
CTS is secure and safe to use – Mr Ahanogbe
Accra, May 19, GNA – Mr Fred Clinton Ahanogbe, a focal person, Inter-regional Bridge Group, says Ghana’s Case Tracking System (CTS) is 99 per cent safe and secured.He said all the servers on which the application ran were encrypted, end to end.Mr Ahano…